Which party to a contract absorbs the preponderance of cost risk when a Firm-Fixed-Price (FFP) contract is used?


A) the seller
B) the buyer
C) the cost risk is equally shared.
D) the insurer

E) All of the above
F) A) and C)

Correct Answer

verifed

verified

A contract is a unilateral document that binds a seller to provide specified products and services under terms agreeable to the buyer.

A) True
B) False

Correct Answer

verifed

verified

The extent to which a project relies upon internal sources for materials and services varies from one project to another and from one organization to another.

A) True
B) False

Correct Answer

verifed

verified

All of the following factors are commonly used to assess potential suppliers pursuant to a source selection decision EXCEPT:


A) supply quality
B) personal relationships with senior management
C) inbound transportation cost
D) replenishment lead time

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

On complex projects,despite the importance of factors such as technical capability,managerial capability and previous experience;the ultimate driving factor is almost always the price of the proposal.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is one of the PMBOK's four project procurement management processes?


A) Administer procurements
B) Perform configuration management
C) Conduct contract reviews
D) Perform value engineering

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

Traditional project procurement was characterized by relatively few contract claims,whereas contemporary project partnering has resulted in a significant increase in the frequency of contract claims.

A) True
B) False

Correct Answer

verifed

verified

False

Project managers must frequently decide whether to obtain needed products and services from internal sources or from external sources. This decision is often referred to as the "make or buy" decision. Briefly identify and explain at least three reasons that support the decision to "make" the products and at least three reasons that support the decision to "buy" the products.

Correct Answer

verifed

verified

Answerwers will vary

Compare and contrast traditional project procurement management with the more contemporary approach - project partnering. What are the advantages associated with project partnering?

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

Traditional project procurement manageme...

View Answer

Project partnerships offer which of the following advantages to both clients and vendors?


A) shared motivation
B) potential of lower cost for client
C) potential of greater profit for vendor
D) opportunity for vendor to prove oneself

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

All of the following entities are typically included in the supply chain EXCEPT:


A) suppliers
B) public relations
C) consumers
D) project team

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Extensive supplier evaluation approaches such as surveys,facility visits and financial analysis should be applied to first-tier suppliers only.

A) True
B) False

Correct Answer

verifed

verified

Project procurement management includes six processes. Identify and briefly describe the first five processes that constitute project procurement management.

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

1. Plan Procurement Management: This pro...

View Answer

A project organization can serve as either the buyer or the seller in a project related contract.

A) True
B) False

Correct Answer

verifed

verified

Fixed price contracts provide low risk for the seller,since the buyer will pay a fixed price,regardless of how much the project actually costs the seller.

A) True
B) False

Correct Answer

verifed

verified

False

Supply chain management focuses exclusively upon the parties directly involved in providing supplies to the project team.

A) True
B) False

Correct Answer

verifed

verified

Logistics,in contrast to supply chain management,is the work required to move and position inventory throughout a supply chain.

A) True
B) False

Correct Answer

verifed

verified

All of the following accurately describe the features and characteristics of a contract EXCEPT:


A) A contract binds both the seller and the buyer.
B) A contract obligates the seller to provide a specified product or service.
C) A contract obligates the buyer to pay for a specified product or service.
D) The project organization is always a buyer in a contract arrangement

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Among the disadvantages associated with outsourcing is the potential loss of special skills for doing the outsourced activities.

A) True
B) False

Correct Answer

verifed

verified

Which of the following terms describes a method for transforming contractual arrangements into a cohesive project team with a single set of goals and established dispute resolution procedures?


A) a contract unification plan
B) partnering
C) arbitration
D) conflict resolution

E) A) and B)
F) A) and C)

Correct Answer